What happens during a home EV charger installation?

The short answer

A typical home EV charger installation has five stages: an assessment of your supply and switchboard, choosing the charger location, the installation by a registered electrician, testing, and a handover with paperwork. How long it takes and what it involves depends on your property and the charger.

If you have never had an EV charger installed, it helps to know what to expect. Here is how a typical installation unfolds. The details change from home to home, so treat this as a general picture rather than a fixed recipe.

Stage 1: The assessment

Everything starts with looking at what you have. Before any equipment is ordered, an electrician will usually want to understand:

  • Your car and how you use it. What its maximum AC charging rate is, how far you drive and when it is parked at home.
  • Your electrical supply. Whether you are on a single phase or three phase supply and what your incoming supply can handle.
  • Your switchboard. Its condition, whether there is room for the protection the charger needs, and what else it supplies.
  • Your household load. Hot water, heating, cooking and other large appliances that may be running while the car charges.

The EWRB notes that for chargers above 15 amps, the installer must make sure the incoming mains will not be overloaded, and that maximum demand and voltage drop are checked. This stage is where those questions get answered.

The assessment decides everything that follows, including whether any supply or switchboard work is needed first. It is also when you get an honest quote, because the electrician has seen the property.

Stage 2: Choosing the location

Where the charger goes is more than a matter of looks. Common points to consider:

  • Reach. It needs to be close enough that the cable comfortably reaches the car's charging port, including if you sometimes park the other way around.
  • Distance from the switchboard. A shorter, simpler cable route is usually easier, but it is not the only consideration.
  • Weather exposure. Outdoor locations need equipment suited to the conditions, and Dunedin is not short of weather.
  • Everyday use. Think about where people walk, how doors and garage doors open, and where the cable will rest when not in use.
  • Future plans. If you might get a second EV, say so, as it can affect planning.

Stage 3: Choosing and confirming the charger

With the assessment done, you will settle on the charger itself, including whether it is tethered or socketed and what smart features it has. WorkSafe suggests asking the supplier for the Supplier Declaration of Conformity before you buy, as assurance that the equipment is suitable for New Zealand, and giving it to your electrician to review.

Stage 4: The installation

WorkSafe says a wall-mounted charging unit at home must be installed by a registered electrician. In general terms, a dedicated circuit is run from the switchboard to the charger. The EWRB recommends a dedicated sub-circuit from the main switchboard, rated for the expected load. The appropriate protection devices are fitted, the charger is mounted and connected, and the work is made tidy.

WorkSafe's guidance notes that some older wiring may need upgrading, since high-draw devices can create heat that older wiring was not designed to handle. That is another reason the assessment comes first.

Because the work involves the main switchboard, it may also need to be inspected by a licensed inspector, which your electrician arranges. WorkSafe notes that the law requires some electrical work, particularly work on the main switchboard, main cable and main earth, to be inspected.

Stage 5: Testing and handover

Once the installation is finished, the electrician tests the work before handing it over. At handover you should expect:

  1. A walk-through of how to use the charger, including any app or scheduling.
  2. An explanation of any settings, such as charging times or current limits.
  3. A Certificate of Compliance for the fixed wiring work. The EWRB advises attaching the charger's supplier declaration of conformity to it.
  4. Any manufacturer warranty information.

Keep the paperwork with your house records. WorkSafe notes that a Certificate of Compliance may be needed for insurance claims or when you sell.

What can change the process

Not every installation follows this path. The process can look different if:

  • Your supply or switchboard needs work before a charger can go in.
  • The charger location is a long way from the switchboard, or the route is difficult.
  • Your property needs approvals or notifications beyond the electrical work itself.
  • The charger you choose has particular requirements.

If your electrician explains why your job differs from the typical picture, that is a good sign: it means they have looked at the property.

Next steps

If you are thinking about a home charger, the best first step is a conversation and a site assessment. Honest Electrical is an Evnex Installation Partner in Dunedin. Find out about our EV charger installation service and we will talk through what your home needs.

Sources and further reading

FAQs

Common questions

How long does an EV charger installation take?

It varies with the property, the cable route and any supply work needed. Your electrician can give you an idea after assessing your home.

Do I need to be home during the installation?

Usually someone needs to give access, and a handover at the end is useful. Check with your electrician what they need for your job.

What documents should I get when it is finished?

A Certificate of Compliance for the fixed wiring work, with the charger's supplier declaration of conformity attached, according to the EWRB. Keep them with your home records.